VKF Renzel Expands its Logistics
In August 2023, construction work began at VKF Renzel GmbH for the expansion of the logistics hall with Giesers Stahlbau GmbH.
The construction of the logistics hall will provide VKF Renzel with up to 6,000 additional pallet spaces at its headquarters in Isselburg. For customers, this means that they will have access to an even larger assortment and even more products will be available from stock.
Just like the adjacent halls, the new warehouse, which will be completed in spring 2024, will also have its own power supply. The electricity will be fed in from the company's own solar power system on the roof. With this future-oriented and sustainable measure, VKF Renzel GmbH is creating an even better CO2 footprint.
Length
101.00 m
Width
41.00 m
Height
11.5 m
Building Footprint
4164.00 qm
Steel Construction
163.00 to
Total Size
3950 m²
Länge
101,00 m
Breite
41,00 m
Höhe
11,5 m
Gebäudegrundfläche
4164,00 qm
Stahlkonstruktion
163,00 to
Gesamtgröße
3.950 m²